  • Sunset existing image ordering request system (Phoenix) and replace with Jira Service Desk

  • Implement in parallel to the Net X Digital Asset Management system implementation and go live when Net X launches in Fall 2020

  • Separate database from request system

  • Implement new and improved request system (new features, new workflows, improved forms, etc.)

  • Implement the basic requirements with our in-house Jira developer

  • Implement advanced requirements utilizing Isos Technologies as the primary developer

3. Scope

3.1 Basic Configuration of JSD( Jira ServiceDesk) required for the integration.

3.2 CTI App Integration

3.3

...

Net X API Integration

4. Out of Scope

4.1 Basic requirements (this work to be done by AIC developer)

...

6. Work Breakdown Structure ( WBS)

7. Dependency

Sl No

Items

Phase

Remarks

1

Access of JSD to test the integration

2

Access of Server to deploy the attachment service.

3

Availability of Artic team for any queries

Requirement Gathering/Development/Integration Testing

4

Availability of Artic team for testing

UAT