        YUVARAJ KUNDASI

TasksActivityResponsibility Estimation in hrsStart dateEnd DateStatusComments
1Install Jira Data-center for validating the Add-on. Local Environment




This is required to show to JIRA assessment team
1.1Pre-requisites

Mar-4-2019Mar-6-2019

1.1.1Node-1,2 and3 with Jira installationYUVARAJ KUNDASI (Unlicensed)3

COMPLETED
1.1.2Load BalancerYUVARAJ KUNDASI (Unlicensed)3

COMPLETED
1.1.3Jira DBYUVARAJ KUNDASI (Unlicensed)3

COMPLETED
1.1.4JIRA Instance(Application and Application media storage)YUVARAJ KUNDASI (Unlicensed)3

COMPLETED
1.2Test  app and document the results as defined in the readiness document.   Mar-8-2019Mar-15-2019
Attachment link : https://developer.atlassian.com/platform/marketplace/dc-apps-submitting-your-app/
1.2.1Complete Performance and Scale testing




Ref link: https://developer.atlassian.com/platform/marketplace/dc-apps-performance-and-scale-testing/
1.2.1.1Create User Actions list for the performance testing.Deepthi Reddy N B (Unlicensed)4

IN PROGRESS
1.2.1.2Deploy 3 nodes data center with data.YUVARAJ KUNDASI (Unlicensed)2

TO DOTo be deployed just before testing to save costs.
1.2.1.3Perform and Capture results for the performance actions with and without Add-on scenariosDeepthi Reddy N B (Unlicensed)12

TO DO
1.2.2Scale testing steps & MethodYUVARAJ KUNDASI (Unlicensed)2

COMPLETEDPerformance testing steps for different deployments (1, 2 & 4 ) nodes
1.2.2.1Deploy 1 Node data center with data.
4

TO DOTo be deployed just before testing to save costs.

1.2.2.2

Create User Actions list for the performance testing for 1 node
4

TO DO

1.2.2.3

Deploy 2 Node data center with data.
4

TO DOTo be deployed just before testing to save costs.
1.2.2.4Create User Actions list for the performance testing for 2 node
4

TO DO
1.2.2.5Deploy 4 Node data center with data.
4

TO DOTo be deployed just before testing to save costs.
1.2.2.6Create User Actions list for the performance testing for 4 node
4

TO DO
2Provide support escalation details to Atlassian for Data Center Compatibility  Mar-18-2019Mar-18-2019

2.1Create a clear escalation process for your customers available to Data Center licensed apps
1

TO DO
2.1Define single point of contact (which can be a mailing list) to raise escalations with
1

TO DO
2.1Create and maintain the owner of the app contact in the DCHELP ticket
1

TO DO
2.1Create and communicate Atlassian about SLA with customers on Data Center licensed apps
1

TO DO
3Complete technical review with Atlassian after submitting the readiness document. Atlassian & Empyra40Mar-19-2019Mar-25-2019TO DODependency with Atlassian
4Contingency plan for App changes & review with AtlassainAtlassian & Empyra40Mar-26-2019Apr-2-2019TO DO 
5Add Data Center compatibility to your app descriptor Dipesh Chouksey (Unlicensed)2Apr-3-2019Apr-3-2019TO DO 
6Upload App to MarketplaceKarthikh Pandian
2Apr-3-2019Apr-3-2019TO DO


Total hours144