Tasks | Activity | Responsibility | Estimation in hrs | Start date | End Date | Status | Comments |
---|---|---|---|---|---|---|---|
1 | Install Jira Data-center for validating the Add-on. Local Environment | This is required to show to JIRA assessment team | |||||
1.1 | Pre-requisites | Mar-4-2019 | Mar-6-2019 | ||||
1.1.1 | Node-1,2 and3 with Jira installation | YUVARAJ KUNDASI (Unlicensed) | 3 | COMPLETED | |||
1.1.2 | Load Balancer | YUVARAJ KUNDASI (Unlicensed) | 3 | COMPLETED | |||
1.1.3 | Jira DB | YUVARAJ KUNDASI (Unlicensed) | 3 | COMPLETED | |||
1.1.4 | JIRA Instance(Application and Application media storage) | YUVARAJ KUNDASI (Unlicensed) | 3 | COMPLETED | |||
1.2 | Test app and document the results as defined in the readiness document. | Mar-8-2019 | Mar-15-2019 | Attachment link : https://developer.atlassian.com/platform/marketplace/dc-apps-submitting-your-app/ | |||
1.2.1 | Complete Performance and Scale testing | Ref link: https://developer.atlassian.com/platform/marketplace/dc-apps-performance-and-scale-testing/ | |||||
1.2.1.1 | Create User Actions list for the performance testing. | Deepthi Reddy N B (Unlicensed) | 4 | COMPLETED | Deepthi Reddy N B (Unlicensed) Sharmendra Vishwakarma Automated testing scripts for testing the Add-on on data-center.
| ||
1.2.1.2 | Deploy 1 nodes data center with data. | YUVARAJ KUNDASI (Unlicensed) | 2 | IN PROGRESS | To be deployed just before testing to save costs. | ||
1.2.1.3 | Perform and Capture results for the performance actions with and without Add-on scenarios | Deepthi Reddy N B (Unlicensed) | 12 | TO DO | |||
1.2.2 | Scale testing steps & Method | YUVARAJ KUNDASI (Unlicensed) | 2 | COMPLETED | Performance testing steps for different deployments (1, 2 & 4 ) nodes | ||
1.2.2.1 | Deploy 1 Node data center with data. | 4 | TO DO | To be deployed just before testing to save costs. | |||
1.2.2.2 | Create User Actions list for the performance testing for 1 node | 4 | TO DO | ||||
1.2.2.3 | Deploy 2 Node data center with data. | 4 | TO DO | To be deployed just before testing to save costs. | |||
1.2.2.4 | Create User Actions list for the performance testing for 2 node | 4 | TO DO | ||||
1.2.2.5 | Deploy 4 Node data center with data. | 4 | TO DO | To be deployed just before testing to save costs. | |||
1.2.2.6 | Create User Actions list for the performance testing for 4 node | 4 | TO DO | ||||
2 | Provide support escalation details to Atlassian for Data Center Compatibility | Mar-18-2019 | Mar-18-2019 | ||||
2.1 | Create a clear escalation process for your customers available to Data Center licensed apps | 1 | TO DO | ||||
2.1 | Define single point of contact (which can be a mailing list) to raise escalations with | 1 | TO DO | ||||
2.1 | Create and maintain the owner of the app contact in the DCHELP ticket | 1 | TO DO | ||||
2.1 | Create and communicate Atlassian about SLA with customers on Data Center licensed apps | 1 | TO DO | ||||
3 | Complete technical review with Atlassian after submitting the readiness document. | Atlassian & Empyra | 40 | Mar-19-2019 | Mar-25-2019 | TO DO | Dependency with Atlassian |
4 | Contingency plan for App changes & review with Atlassain | Atlassian & Empyra | 40 | Mar-26-2019 | Apr-2-2019 | TO DO | |
5 | Add Data Center compatibility to your app descriptor | Dipesh Chouksey (Unlicensed) | 2 | Apr-3-2019 | Apr-3-2019 | TO DO | |
6 | Upload App to Marketplace | Karthikh Pandian | 2 | Apr-3-2019 | Apr-3-2019 | TO DO | |
Total hours | 144 |
- Data-Center Monitoring documentation
- JConsole Monitoring
- Monitoring Application & database connection usage in Jira
- Performance and Scale testing Sample
- Jira Data generator