Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Tasks

Description

Estimated Efforts(hrs)

1

UI

1.1

Create an Atlassian project with pre-requisites.

create a cloud project with pre-requisites

2h

1.2

Create an UI with an Add Projects Field, Date Range Field, Worklog Data Button, and Worklog Data Table.

complete UI design

14h10h

2

Business Logic

2.1

List the APIs and check with Postman.

3h

2.2

Script for the frontend to get user-entered data from the UI.

will have the user enter details

6h

2.3

Get the project list.

Call APIs and get the details

3h

2.4

Get the issue list.

Call APIs and get the details

3h

2.5

Get the worklog data.

Call APIs and get the details

3h

2.6

Get the worklog data in the UI table view.

4h

2.7

Get the worklog data in a csv file with the click of the csv download button.

Create a CSV to get the worklog data

5h

2.6

Testing

2h

3

Logger Implementation

3.1

logger implement

7h

4

End-to-end testing

Complete process testing

4h

Total Estimation Time

56h52h