No | Task | Estimation (hrs) | Comments | Dependency of tasks (Y / N) |
---|---|---|---|---|
1 | Create Connection | |||
1.1 | UI for adding connection details, and test connection | 8 | N | |
1.2 | Back end for adding, testing and saving the connection to DB | 16 | ||
2 | Fetching AD fields | |||
2.1 | UI to select AD fields that needs to be synced to Jira | 8 | ||
2.2 | Back end for fetching AD fields | 16 | ||
2.3 | Back end to save the selected AD fields in DB | 16 | ||
3 | Field Mapping | |||
3.1 | UI to select custom field mapping | 16 | ||
3.2 | Back end to save the custom field mapping in DB | 16 | ||
4 | Synchronization | |||
4.1 | UI to select the time of sync | 8 | N | |
4.2 | Back end to save the sync time in DB | 16 | N | |
4.3 | Back end to sync AD fields to Jira | 20 | ||
5 | Configuration | |||
5.1 | UI for showing the config with options such as Reset, Edit, Delete, Disable | 10 | ||
5.2 | Back end to update, delete and disable the config options | 16 | ||
6 | Testing and Documentation | |||
6.1 | Testing the plugin | 8 | ||
6.2 | Updating the Document | 8 | ||
Total | 182 |
...